The CS also inquired about the status of the blocks constructed at each of the 12 locations in different districts of the valley. He also stressed on mandatory completion of all these blocks as per the stipulated time limit.

Secretary, DMRR&R, Anil Kaul said that out of the total 6000 flats to be built for the same number of employees, about 4800 have already been taken up for completion at various locations.

He said that so far construction of 2088 flats has been completed, out of which 998 have been allotted to genuine applicants.

He said that work on 2712 flats is in the final stages of completion and these will be handed over for allotment in the next few months.

Anil Kaul, Secretary, DMRR&R, said, “Since the beginning of April this year, construction work of 536 new flats was taken up and 392 flats were also completed, resulting in about 144 flats during this period. “Increased.” meeting.